The first picture shows the fully compacted site -- those strange markings coming from the compacting roller on the left.
Tuesday, August 19, 2008
The Build finally starts
The first picture shows the fully compacted site -- those strange markings coming from the compacting roller on the left.
Sunday, July 20, 2008
And we thought soil was just soil
We were obviously aware that the center of the site was higher than the sidewalk (formally validated by a survey) and our design took advantage of this to provide interesting steps up to the front door. We also wanted to ensure the sliders out to the patio did not require a step down, so the house is designed on two levels, with the kitchen and dining/living area being 1 foot lower than the rest, something which cannot be seen from the outside. To achieve this, we knew we would need some soil to be taken out.
Our builders concerns related to the nature of the soil -- '' a lot of organic matter" -- and why our lot had that "domed" perspective when the others nearby did not. So he suggested a soil test, which involves soil engineers drilling and taking core samples. The results were not good for a slab-based house, particularly one in an earthquake zone, and were advised to have the soil compacted.
This involved his folks, using special rented machines, digging out the soil and recompacting back in layers, with the soil engineers retesting at each stage. A costly, non-budgetted, item which added 4-5 weeks to the timeline.
This picture illustrates what went on. We gather that the neighbors thought were building a basement!
Sunday, May 18, 2008
Demo and site prep
Thursday, May 15, 2008
Obtaining planning permission
This came about because the covered patio "structure" intrudes into the setback area on the house frontage street and we had assumed that this would not be of concern because it would be behind a fence. So we had to submit some supporting documentation related to why we need to do this because of our triangular lot.
So it was mid-May before we were finally signed off and folks who are experienced in this stuff tell us that getting it in 6 weeks was still really fast.
Friday, January 18, 2008
Key decisions within the design details
- While J wanted a kitchen that is not fully the "open plan" style seen in many modern homes, an acceptance of a design that partly opens the dining room/kitchen wall, with a horizontal "pass-through," plus this wall not going right up to to the sloping ceiling.
- Aluminum framed windows and exterior doors, both for the look and for no maintenance. All windows and doors going to the ceiling line, again as part of the look.
- Space-saving, in-wall pocket doors wherever feasible for the interior.
- No air conditioning so a lot of attention to cross ventilation, facilitated by three center hallway, operable skylights and also an operable internal window above the bedroom doors near these skylights - which also provide more natural light into those areas.
- The uses of structurally insulated panels (SIPS) for external walls, providing greater insulation and less waste from stick-frame construction. (Our builder had used these on a recent house.)
Tuesday, January 15, 2008
Developing the plan details: Lessons learned
For example, our builder had provided a fairly detailed, line item estimate, based on recent houses using comparable materials and finishes. So, starting on the detailed design of windows and glass/metal framed exterior doors (W&Ds), we would check with him as to what assumptions he had made to get to his #. We would then use his #s to calculate the likely cost of the number and nature of our wish list of W&Ds.
In conversations with our architect about their number, placement, size and operability, we would then raise cost parameters and his responses left us feeling he was less cost sensitive than us. In discussing this, he defended his process as "you do not design to a budget" but develop your design and then cost it and "re-engineer" if necessary. Given we had that detailed, line item estimate/budget, we wanted to limit the number of costing and re-engineering steps. So we ended up "negotiating" a design process we could all live with.
So we offer the following counsel to anyone reading this with the intent of building their own home:
1. Have your architect articulate his/her design process, preferably with examples, from Day One and, if necessary, amend the process so you are all comfortable with it. Also, have a "process check" discussion every now and again.
2. Try to find a builder who'll provide a detailed, line item estimate/budget based on a "Preliminary Bid Instructions" package, to learn what the major cost drivers are. If some elements are not yet included, keep them on the list as pending, so you do not lose track of them.
3. Remember that the builder has made certain assumptions for each line item, so whenever you feel that your more detailed design and material choices for a particular element might be problematical, check with him/her.
4. Take full advantage of your builder's and/or architects access to current houses when you want to remind, or educate, yourself about what certain materials look like "in situ" or how certain things work, like the different window operability options. You never want to end up saying "I didn't know it would look, or work, like this!"
Saturday, December 1, 2007
Selecting a Builder
One bid, from the largest company of the four, was 25% more than the other two, so the choice was between two similar bids. One of these was from a builder with more "green" experience, so after one more visit to his most recent house -- including a walk-through with him, discussing choices and specs -- we elected to go with him.
So the start of 2008 has us us with an agreed design, a floor plan (which just needs a few tweaks,) and a builder. So now we start on the more detailed planning and permitting phase with target date to start the demolition and build no later than April 1, 2008
Saturday, November 10, 2007
Final steps with the Design
As can be seen, this still has the sloping roof elements at each end but a flat roof in the middle. So while the living/dining area on the left-side roof will have clerestory windows on three sides, the only clerestory windows in the right-side roof area will be over the garage, so none in the rear over the master bedroom area. We agreed that this would work for us and still give the house its "feature roof."
So the last steps in this phase are for our architect to provide us with the final floor plan and to develop a list that will help builders/GC's ballpark some prices.
Friday, October 12, 2007
Design Process: Step 2
We had a very positive reaction to the overall design, which had double butterfly roof over the main, rectangular module. We also liked the idea of a block "feature wall" which he proposed to continue inside the house, showing the exposed block.
We then reviewed the floor plan and how our room wish-list had been accommodated and found we had everything (excluding the garage) in approx. 2550 square feet.
He then asked us to take some time to go over the proposal and we initially focused on our room size wish list -- rechecking why we arrived at such #s and and either getting comfortable with them or tweaking them.
We then reconsidered the house's double butterfly roof line and started to imagine ourselves in the rooms this covers.
Obviously, it will give us the high ceilings and light we want in the living/dining space but when we considered this in the rest of house it raised some questions. The first was how light would enter the smaller rooms like the laundry and the second bath. The second, more significant issue for us, was how much light would be entering all three bedrooms as we like dark bedrooms for sleeping and do not want have to devise window coverings for angled windows.
We decided to revisit this with our architect and seek advice on whether such a roof can work aesthetically if one chooses not to have glass in certain sections, or whether there are other roof designs that still give us a "feature roof" without so much natural light coming into the bedrooms.
Friday, October 5, 2007
Design Process: Step 1
Our architect asked for an initial 2 hr meeting to gain a good sense of our design preferences and the specific needs we want this house to meet – and that we should bring any relevant photos and anything else that would help.
The discussion beyond these more specific aspects was more intriguing as we sensed our architect wanted more specifics on our design choices -- beyond those house photos we had selected. So he asked us to comment on some pictures of elements of Palm Springs houses. Looking back, we feel we had possibly avoided getting too specific on design elements as we really want him have some freedom and potentially test us with ideas we may not have considered.
Thursday, October 4, 2007
Our green education
The efficient aspect was easy, starting with the use of tankless water heaters and radiant floor heating. Optimization of natural cooling opportunities through window selection and placement was another obvious aspect. Next was achieving efficient heating and cooling through solar-generated electricity and solar-heated water, both of which we had seen in some houses. Given our site, solar electricity quickly emerged as a fairly obvious choice, particularly as our long term plans for this home allow return-on-investment models with longer periods.
An inevitable question with such equipment is where it will be placed, as we do not want our home to have "racks" and other hardware projecting above those flat and/or slightly sloping roofs. Fortunately, we learned that for our site's solar orientation the solar panels can be placed almost flat with only a 5% reduction in efficiency.
As to the selection of other products and materials that are green, our architect has experience in these areas, plus our reading and research continues.
Monday, October 1, 2007
Designs in line with emerging preferences



Two of these houses have different roof levels within the one structure, and some of those roofs also have some slope -- something that interests us as we had began to think of our house as two modules, one with the garage, bedrooms and bathrooms, and the other for living, dining and the kitchen. Two also have clerestory windows, with high ceilings, a common feature in modernist houses. Also their frontage is broken up by how certain aspects are set back, plus none of them have elements that we feel would look out of date in the future.
Given these preferences, we inevitably like the following house, from the portfolio of our chosen architect who had also satisfied our other criteria.
Sunday, September 30, 2007
Our evolving preferences
While such architects will (truthfully) tell you they can design all types of modern houses we inevitably saw preferences in design elements, such as how one favored horizontal wood elements on doors and balconies, while another favored metal for siding and to face garage doors. While we have often noted and liked houses that use such elements we were also conscious of some possibly looking out-of-date in the future -- and remember this is our "last house" which we hope to live in for a long time.
So it was back to looking at more house photos and the breakthrough came when J articulated that we wanted a modern home, with "mid-century modern" influences, that would look "timeless," such as many of the homes we had seen on our Palm Springs visits.
Remember, we are still not at the point of agreeing an actual design, but getting to the next level of direction -- to help us select, and then instruct the architect.
Friday, September 28, 2007
Finding/selecting an architect
We next went through the Web sites of architects of interest, developing a list of eight that we contacted by email, asking them to meet us. Our email briefly described our goal and the initial meetings started at the site, as we wanted to observe their reactions to it .
In preparation, we developed an agenda, which evolved through our meetings, as we added to our knowledge, -- such as the importance of an architects access to, and relationship with, general contractors (GC) with experience of building in the modern style.
For us, the following criteria evolved and they determined our short-list and then the final selection:
- Nature of the architects' work todate and how that fitted our (admittedly evolving) preferences.
- The likely cost of of this type of work, based on more recent projects.
- The quality of these recent projects, accepting a lot of that falls on the GC but trying to establish how the architect has influenced, or not influenced, this.
- That amorphous thing called "chemistry," in terms how we would feel working with this person.
Tuesday, September 18, 2007
Pictures of our lot
The original house, from the garden area in narrow point of the triangle. Also, from the street, which will be at the rear of the new house.
Then a street view of the lot from our "new street." and lastly a view looking down the triangle, which will be the view from our living area. Note no houses in sight!